This FlexSim Community Forum is read-only. Please post any new questions, ideas, or discussions to our new community (we call it Answers) at https://answers.flexsim.com/. Our new Question & Answer site brings a modern, mobile-friendly interface and more focus on getting answers quickly. There are a few differences between how our new Q&A community works vs. a classic, threaded-conversation-style forum like the one below, so be sure to read our Answers Best Practices.


flexsim.com

Go Back   FlexSim Community Forum > Flexsim CT > Container Terminal (CT) Library
Downloads

  #1  
Old 06-30-2011
James Morley James Morley is offline
Flexsim User
 
Join Date: Oct 2008
Posts: 2
Downloads: 37
Uploads: 0
Thanks: 2
Thanked 0 Times in 0 Posts
Rep Power: 0
James Morley is on a distinguished road
Default Double Hoist Cranes

Hi, On a simulation project we have been asked to look at planned equipment procurement and simulate the terminals future capacity. Is it possible to simulate Tandem lift 2x40' (double hoist) cranes yet please as this is one of the options they want to look at?

I've already looked into doing it by working out productivity of a dual hoist crane seperately and then using a Time per move approach in the CT model, but have been told that this doesn't really match their requirements and they want to use real crane speeds and view the animation correctly.

My other idea was to double the number of cranes and slow the speeds by a factor to mirror the dual hoists but I think this might also be unacceptable to them. Are there any other ways / better ways, ideas to simulate this please?

Thank you, James
  #2  
Old 06-30-2011
LINWEIXU
Guest
 
Posts: n/a
Downloads:
Uploads:
Default

I think you can use combiner,and then change Combiner Component List and setloc ,finish handing ,the Separate. like attach video
Attached Files
File Type: zip 双小车集装箱装卸过程-初稿.zip (457.1 KB, 257 views)
The Following User Says Thank You to For This Useful Post:
James Morley (07-08-2011)
  #3  
Old 10-22-2012
stmyint stmyint is offline
Flexsim User
 
Join Date: Oct 2012
Posts: 14
Downloads: 6
Uploads: 0
Thanks: 6
Thanked 1 Time in 1 Post
Rep Power: 92
stmyint is on a distinguished road
Default

Hi James,
Did you fix this double hoist crane problem?
cos i also have that kind of problem. Please let me know & share if you already fixed it.

Thanks,
Si Thu
  #4  
Old 10-22-2012
Hao Zhou's Avatar
Hao Zhou Hao Zhou is offline
Flexsim User
 
Join Date: Sep 2010
Location: Long Beach
Posts: 66
Downloads: 56
Uploads: 0
Thanks: 78
Thanked 43 Times in 25 Posts
Rep Power: 146
Hao Zhou will become famous soon enoughHao Zhou will become famous soon enough
Default

I think you may create another spreader under attribute "drawsurrogate". When loading or discharging a container, you need to figure out the kinematics of second spreader. In the same time that the quay crane is loading and discharge, you draw another box under the second spread in ondraw trigger. This is a kind of cheating, and you also need extra work to make sure productivity is right.

Tags
dual hoist


Thread Thread Starter Forum Replies Last Post
Multiple Cranes - best way JMEngelhart Tips and Tricks 4 03-09-2015 09:30 AM
About Double trolley Over Head Crane... syseo Q&A 2 06-23-2011 07:04 AM
Isolating Operator from overhead cranes Nathan Dwyer Q&A 1 08-27-2008 06:25 AM
Can’t stop cranes colliding Kenny Macleod Q&A 8 07-16-2008 10:18 AM
Double load handling ASRS Paul Dowling Q&A 8 05-06-2008 10:19 PM


All times are GMT -6.
Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2020, vBulletin Solutions Inc.
Copyright 1993-2018 FlexSim Software Products, Inc.