ATTENTIONThis FlexSim Community Forum is read-only. Please post any new questions, ideas, or discussions to our new community (we call it Answers) at https://answers.flexsim.com/. Our new Question & Answer site brings a modern, mobile-friendly interface and more focus on getting answers quickly. There are a few differences between how our new Q&A community works vs. a classic, threaded-conversation-style forum like the one below, so be sure to read our Answers Best Practices. |
flexsim.com |
#1
|
|||
|
|||
how to assign a defined run time to a processor
Hi all,
I'm trying to define a yearly run time to all the processors in our model. Let's say availability of machine a) 3400h/a and machine b) 2500h/a. The machines should stop working/go down once they've reached their individual "yearly process time limit". What happens in our model, is that the machine is going down when the total time (e.g. simulation time of 2500h) is reached. machine b) has just been processing for 200h at this point. How can I change this? What is the correct section - MTBF??? Thanks for your ideas! Martin |
#2
|
||||
|
||||
Hello Martin,
that is correct. Use on the Breakdown Tab "Apply MTBF to a set of states" > processing. That will work for the first year, then it becomes a bit tricky. Jörg |
#3
|
|||
|
|||
Setting Yearly Time Limit
Hi,
I have a bit of a work around, Firstly create shift patterns for each processor. You can create labels on each processor to record the available time per shift for the specific processor and then also the allowed total annual allowed available time per processor. In the time tables resume/stop object triggers simply check whether or not the processor has exceeded it allowable time. If it has been exceeded the processor will not be taken out of its down state and thus remain unavailable. I have attached a small demo model. Hope this helps. |
The Following 3 Users Say Thank You to Ian Collins For This Useful Post: | ||
Tom David (01-27-2014) |
Thread | Thread Starter | Forum | Replies | Last Post |
Multiprocessor / read of self-defined process | Marco Bergmann | Q&A | 1 | 11-13-2013 12:59 PM |
Building logic for Delayed Processing Time of Processor - help required | balakrishnan | Q&A | 1 | 07-11-2013 04:14 PM |
Getting parts from three conveyors in our defined order | Radhakrishnan R | Q&A | 6 | 10-16-2012 03:11 AM |
Unknown setup time of a processor | Stefan Trabut | Q&A | 3 | 04-02-2011 07:22 AM |
Assign Operators to Scheduled Down Time | jspeece | Q&A | 1 | 09-04-2009 01:47 PM |