ATTENTIONThis FlexSim Community Forum is read-only. Please post any new questions, ideas, or discussions to our new community (we call it Answers) at https://answers.flexsim.com/. Our new Question & Answer site brings a modern, mobile-friendly interface and more focus on getting answers quickly. There are a few differences between how our new Q&A community works vs. a classic, threaded-conversation-style forum like the one below, so be sure to read our Answers Best Practices. |
flexsim.com |
#1
|
|||
|
|||
Passing task between 2 operators
I am simulating a manufacturing process where the process cycle time (~16 hours) is longer than one shift. The process requires an operator to be utilized during the entire task. Is there a straightforward way to interrupt the operator at the end of their shift, and deliver the partially completed task to a second shift operator? I apologize if this is an overly-simple question. Im fairly new to Flexsim, but I haven't been able to find a solution to this scenario posted yet.
Thanks! |
#2
|
||||
|
||||
hi,
you can give the Operator another tasksequence, which preempting parameter is preempt only. This tasksequence can contain a delay task. If you connect the operator to the other operator with object connection "a"-key, the interrupted tasksequence is moved to the other operator. I test this in a few hours. It works! Jörg Last edited by Jörg Vogel; 07-17-2013 at 01:36 AM. |
Thread | Thread Starter | Forum | Replies | Last Post |
operators passing one another on network node | danielle paniccia | Q&A | 1 | 07-07-2013 04:10 PM |
Non Passing for TEFlowitem | Sung Kim | Q&A | 0 | 05-24-2013 09:51 AM |
What's the meaning of 'non-passing' of yellow tape in networknode? | syseo | Q&A | 1 | 12-22-2012 12:23 PM |
Passing parameters in executefsnode | Sung Kim | Q&A | 2 | 06-01-2010 09:37 AM |
Passing strings into a usercommand | Nico Zahn | Q&A | 6 | 01-13-2010 11:20 AM |