ATTENTIONThis FlexSim Community Forum is read-only. Please post any new questions, ideas, or discussions to our new community (we call it Answers) at https://answers.flexsim.com/. Our new Question & Answer site brings a modern, mobile-friendly interface and more focus on getting answers quickly. There are a few differences between how our new Q&A community works vs. a classic, threaded-conversation-style forum like the one below, so be sure to read our Answers Best Practices. |
flexsim.com |
#1
|
|||
|
|||
How to process with 2 processors at the same time
I wonder i someone can help me with this.
I have 2 processor: Processor 1 and Processor 2. I need to process persons but i need to set when #1 is processing, # 2 is depending on #1, and should wait for #1 until it finish processing altough it is receveing persons from other processors. |
#2
|
||||
|
||||
My first idea would be to control the Processor #2 from Processor #1.
OnEntry: stopobject() OnProcessFinish: resumeobjet() You need a pointer to Processor #2, which could be a center port connection (centerobject(current,1)). This should work.
__________________
tom the (A)tom: "We have solved our problems ... now we have to fight the solutions." |
The Following User Says Thank You to Tom David For This Useful Post: | ||
wilmermoncada (11-25-2009) |
#3
|
||||
|
||||
Don´t really know, if I understood your problem right. Probably it would help to use only one person which is used in both Processors or try it out with connecting both Processors per CenterPort and then close and open the Input Ports of even the other Processor, while one is working.
Sorry, if I understood you completely wrong. This way it would be better to load up an example modell. |
Tags |
processor, same time |
Thread | Thread Starter | Forum | Replies | Last Post |
Picking process | Simon Farsah | Q&A | 9 | 03-23-2015 06:55 AM |
different process times | mohanboyapati | Q&A | 1 | 11-02-2009 11:59 AM |
All time related values 0,0000001 time units delayed | Patrick Cap | Q&A | 2 | 05-01-2009 01:50 AM |
Re-entrant Process | ankus d | Q&A | 2 | 02-09-2009 07:53 PM |
operators working together to decrease process time | Alex Christensen | Tips and Tricks | 4 | 07-14-2008 09:22 AM |