Thank you indeed for your comment.
The issues is that not all this is going to be decided at the same place.

a processor tells the transporter to deliver this to certain network node or any other location and wait to be discharged.
Then the crane needs to find location where it want to put the box.

If processor decides for this, it happens that before the box arrives at crane the place is already occupied by the transporters who arrived before us.

So one way is to stop the transporters at the quay crane and then put some script for transporter to release/deallocate them.

what would be the best strategy here.

thank you in advance.